Brandon Boulevard Construction: What's Finished, What's Next, and What Drivers Should Know |
Major pipeline tunneling is complete beneath Brandon Boulevard, but Moon Avenue closures and construction disruptions will continue as crews move into the next phase of work. |

By Ralph | Crosstown Journal | October 20, 2026
There's encouraging news for Brandon motorists and businesses as crews working on the South Hillsborough Pipeline have completed a major construction milestone beneath Brandon Boulevard.
According to Tampa Bay Water's October 9 project update, the underground microtunnel installation beneath Brandon Boulevard is finished, and restoration work is now underway.
But while that phase of construction is complete, drivers should expect additional disruptions in the surrounding area over the coming weeks. When Will Moon Avenue Reopen?
Project officials anticipate restoring access to North and South Moon avenues at Brandon Boulevard by early November, weather permitting.
However, construction along North Moon Avenue is expected to continue through late December.
The work involves installing pipeline sections through an open trench, with North Moon Avenue closed to through traffic between Victoria Street and Brandon Boulevard.
Local access arrangements may change as construction progresses. Drivers should follow posted detours and allow additional travel time. Local Businesses Remain Open
One important message from project officials is that businesses along the construction corridor remain open and accessible.
Among the establishments highlighted by the South Hillsborough Pipeline project are Arnold Dentistry, Brandon Medical Center, and Nothing Like Us Detailing.
Construction can make familiar routes less convenient, but residents can continue supporting neighborhood businesses while work progresses. What Is the South Hillsborough Pipeline?
The project is part of a major water infrastructure investment designed to expand the regional water supply system serving southern Hillsborough County.
The approximately 26-mile pipeline will connect regional water facilities and help deliver additional drinking water capacity to growing communities.
Construction is scheduled to continue into 2028, with restoration activities extending into 2029. What Brandon Residents Should Know
Although the tunneling beneath Brandon Boulevard is complete, the surrounding work is not.
Residents traveling through the Moon Avenue corridor should watch for changing traffic patterns, temporary closures, and construction equipment.
For current construction notices, detour information, and project updates, visit: https://southhillsboroughpipeline.com/detours-alerts/
Residents with questions can also contact the project team at 813-485-6480.
The bottom line: A significant portion of the Brandon Boulevard work has been completed, but patience and caution will still be needed as crews continue construction and restoration nearby.
|